Case Study

Transforming travel experiences, enhancing public transport and promoting sustainability

Lincolnshire County Council shelter upgrade programme

Three phases.
Three different challenges.
One consistent approach.

Understand the site, question the assumptions, and get it right before anything goes in the ground.

We supported the council through a meaningful community engagement process that shaped the final scope. We identified the groundworks saving opportunity before the client had to ask. And we delivered a programme of 57 bus stops upgraded across a large and varied county, in close partnership with Shelter Maintenance, without a single approved installation falling short.

The client’s response when they received our final programme report said it better than we could.

On receiving our final programme report, Lincolnshire County Council told us:

“This captures the amount of hard work that has been undertaken to achieve a really superb improvement on the infrastructure on our roads. Really pleased with how the projects have progressed and the way we have worked through some difficult challenges.”

Project Overview

The 2025–2026 upgrade programme set out to deliver complete bus stop upgrades across Lincolnshire – from city centre stops in Lincoln to rural shelters serving small villages – with a consistent, modern shelter range capable of meeting the varied demands of each location.

We were appointed through the CS Procurement (Kent) Framework. Ahead of each phase, we undertook a detailed survey of every site – establishing precisely what was in place at each stop before any orders were placed.

57 bus stops were upgraded across three phases between January 2025 and May 2026, covering Lincoln, Sleaford, and the wider county area.

Project execution was carried out in close strategic partnership with Shelter Maintenance, who hold the council’s maintenance contract for bus infrastructure across Lincolnshire. Each site was treated as a complete bus stop environment – existing infrastructure removed, groundworks completed, and new shelters, poster cases, flags and timetable cases installed where required, reusing existing fittings where they were still fit for purpose. In many cases, existing posts were removed entirely and flags and cases transferred to the shelter structure itself, reducing clutter on the footway and improving accessibility for passengers.

Surveys, mark-up drawings, traffic management and permits were handled by Externiture as part of our end-to-end programme management; shelters supplied flat-packed to Shelter Maintenance’s depot, their team building and transporting them to site and completing all physical works on the ground. It is a model that works because both sides bring something the other doesn’t – local knowledge and operational reach on their part, product expertise and programme management on ours.
____________________________________________________________________________________________________

Shelter Scope & Configuration

Across all three phases the programme encompassed a wide range of site types, from city centre locations in Lincoln to rural villages across the county. Our Mono® shelter range is designed precisely for this kind of variety – consistent in appearance and quality but easily configured to suit the specific demands of each location.

That flexibility is what makes a programme of this scale coherent. A shelter installed on a busy Lincoln street and one serving a quiet Lincolnshire village look and feel like they belong to the same family – because they do – while being configured quite differently to suit where they sit.

Before any orders were confirmed, our Project Manager reviewed each specified configuration in the context of the site it was intended for. That stage of the process is where experience pays off – and where a programme of 57 installations becomes something more than a list of orders.

Installation types ranged from straightforward like-for-like replacements through to revised site layouts and greenfield installations, each requiring its own level of groundworks and planning input. Where space permitted, we went further than for-like and offered greater protection and improved accessibility rather than simply replicating what was there before. The aim throughout was a better outcome for passengers, not just a replacement shelter. The variety across the programme is a reasonable reflection of what bus infrastructure in a county like Lincolnshire looks like.

 

 

 

Phase 1 – Lincoln

Phase 1 set the template for the programme. 22 bus stops were upgraded across the City, the majority replacing existing structures in the same footprint. Just over a third required revisions to the existing site layout – a reflection of the site-specific assessment that goes into every installation we plan.

Phase 2 – Sleaford

Phase 2 covered six sites in the Sleaford area. The majority of sites replaced existing structures in the same footprint, with groundworks completed by Shelter Maintenance as part of the standard programme scope.

Phase 3 – Lincolnshire County

Phase 3 was the most complex element of the programme. The initial order list of 58 shelters included a number of brick and historic structures in rural settings – shelters that had been designed to sit sympathetically within their surroundings, often in villages with a strong sense of local character. Our Project Manager identified this early and raised it with the client.

Many of these structures, despite their character, presented real accessibility problems. Narrow entrances and raised thresholds made them difficult or impossible to use for passengers with buggies or wheelchairs. Solid construction also meant passengers inside had no view of approaching buses – and drivers had no view of waiting passengers – a functional problem that the new shelters resolve.

These communities often have a strong attachment to their existing shelters. The council engaged with the relevant Parish Councils before committing to those sites – a process we supported fully – so that any concerns could be understood and addressed properly. That conversation led to a revised scope: 29 sites were stood down by mutual agreement, and 29 replacement approvals were confirmed.

____________________________________________________________________________________________________

Smarter Groundworks and Solar Lighting

The groundworks situation in Phase 3 also prompted a closer look. Difficult ground conditions at the first installation flagged that the original specification of dig-in bases across all sites needed reviewing. We carried out a thorough survey of the remaining bases and identified five that were suitable for a bolt-down approach instead – a decision that saved the client over £16,000, and a direct result of responding to what the ground was actually telling us rather than proceeding regardless.

The result was a programme shaped by genuine local conditions and local community input, with every shelter that went ahead doing so with community support.

Ten of the Phase 3 shelters were fitted with solar panels. Connecting shelters to mains power can be both costly and subject to lengthy lead times – solar offered a more cost-effective route to achieving the same outcome. The immediate benefit is light: ten shelters that now provide illumination for waiting passengers. Passenger security at bus stops – particularly at rural stops after dark – is a concern raised consistently by user groups, and shelter lighting is one of the most direct responses available to it.

____________________________________________________________________________________________________

Phased Programme Execution

____________________________________________________________________________________________________

Planning a shelter upgrade programme?

We can survey part or all of your bus stop estate, help you agree priorities based on what the data shows, and then deliver upgrades in a joined-up way. If you are preparing an investment plan or building the evidence for your accessibility statement, we would welcome a conversation.

Contact our team: hello@externiture.com 

Get in Touch